Keep Effort, Scope, And Dates Separate
An estimate can add up and still mislead. In this exercise, check an AI-drafted estimate for a fictional workshop handout against the assumptions the team actually agreed to.
Get The Pack
Give the AI only the test input. Use the separate review key to check its first answer, then compare it with a second run using the worksheet.
Download comparison worksheet (.txt)
Check Three Claims
| Case | Look for | What to verify |
|---|---|---|
| EST-01 | Work hours reported as time until delivery | Preserve the effort unit. Check staff availability and review timing before estimating elapsed time. |
| EST-02 | Optional work included in the base scope | Show the base estimate separately from work that needs approval. |
| EST-03 | A date that overlooks a dependency | Name what must be received or confirmed before promising the date. |
Before sharing a real estimate, distinguish a planning assumption from a commitment. If a date or approval remains open, keep it open in the summary.